These generator interconnection guidelines outline the process, requirements and agreements for installing or modifying generation projects connected in parallel with the DTE Energy electrical system.
Technical requirements (data, equipment, relaying, telemetry, metering) are defined below according to the size and type of generation, location of the interconnection and mode of operation (flow-back or non-flow-back).
These guidelines comply with the Michigan Public Service Commission (MPSC) rules established in MPSC Order-Case U-15787.* The guidelines protect the safety of utility workers, and ensure safe operation of generators and distributed generation units in conjunction with utility company electric systems.
Read a description of DTE Energy's Electrical Distribution System.*
Proposed Guidelines:
- Category 1- Units equal to or under 20 kW*
- Category 2 - Units greater than 20 kW but less than or equal to 150 kW*
- Category 3 - Units greater than 150 kW but less than or equal to 550 kW*
- Category 4 - Units greater than 550 kW but less than or equal to 2 MW*
- Category 5 - Units of 2 MW or greater*
Call the interconnection Hotline at 313.235.4333 if you have questions regarding these guidelines.
These Generator Interconnection Guidelines are not intended for interconnections constructed to accommodate interstate transactions subject to the jurisdiction of the Federal Energy Regulatory Commission (FERC). Entities seeking to interconnect generation for the purpose of engaging in wholesale energy sales should contact the Midwest Independent System Operator, Inc. (MISO) regarding the appropriate procedures for interconnecting directly to the transmission system.
* To view and print this information, you need Adobe® Acrobat® Reader.
Related Links
Overview of the Interconnection Process - High level step by step description of the process, roles, and responsibilities.
Detailed Interconnection Requirements- Detailed information regarding your specific customer generation project, which includes technical requirements.
Equipment list* - Detailed listing of equipment previously inspected by DTE Energy for use on current interconnection projects.
References - Helpful Web sites to complete your project.
Applications and Agreements - When you are ready to move forward with your project to interconnect and operate generation in parallel with DTE Energy complete the application.
Active Interconnection Project Status* - Status by Queue Number of all active interconnection projects.