SolarCurrents Customer-Owned Program Launch Timeline

Offering 1 - 500kW (375kW Res / 125kW Non-Res)Actual Date
Offering launches.01/07/2013 8 a.m.
Application deadline.02/05/2013 5 p.m.
SolarCurrents team completes review of applications.02/12/2013
Random selection event held (if required).02/18/2013
Selected projects posted on SolarCurrents website.02/19/2013
Submit interconnection application. In addition, return SolarCurrents Agreement, signed and notarized.03/19/2013
Submit invoice or project quote, site plan and PVWatts annual solar production form.04/16/2013
Project completion deadline.12/16/2013

 